Lead and lag time are basic project planning and task management concepts within project management. Interviewers ask this question to test a candidate's knowledge of these key concepts.

Karrie Day is a certified career coach and strategist with a passion for helping her clients define and reach their professional goals. She offers career advancement services such as brand development, resume writing and critiques, job search strategies,
Remember to be honest if you do not know the answer to a question like this. While 'I don't know' is not an acceptable answer, pretending to know the answer when you do not is equally as poor of a strategy. Instead, indicate that you are not sure of the answer, provide a guess, and then indicate that you will research this directly after the interview so that you will have the knowledge you need prior to your start date if hired.

Karrie Day is a certified career coach and strategist with a passion for helping her clients define and reach their professional goals. She offers career advancement services such as brand development, resume writing and critiques, job search strategies,
"Lead time represents the time you can plan an overlap between two tasks. For example, let's say you are building a house and you are hanging drywall on the inside of the house. Most other inside tasks are not feasible at that point because of the dust and mess that goes with drywall. However, you can schedule outside tasks such as painting, or landscaping during that time. Lead helps to reduce the overall project time by concurrently executing tasks.
Lag time represents the time you must wait in between tasks. An example of lag would occur when you rough in plumbing and then wait for the inspection and subsequent tasks such as drywall and flooring to be completed before you finish the remaining plumbing tasks like installing the fixtures.
Both concepts are important and necessary aspects of project planning that help project managers ensure that resource optimization rates are high and unnecessary delays are avoided."
Write Your Answer
0 - Character Count
Unlock expert responses that demonstrate your readiness to support complex projects.
Get StartedJump to Question

Written by Karrie Day
30 Questions & Answers • Assistant Project Manager

By Karrie

By Karrie