"Most projects I have worked on have some degree of pressure placed on me. The most recent project where I was placed under extreme pressure was a supermarket build. We had a certain amount of time to complete the project, or the company would be charged a hefty penalty for every day we went over the deadline. The timeline was doable, barring any problems. Everything was running smoothly until a crane collapsed on the project due to high winds, taking out part of the roof and injuring three workers. The job was shut down until an investigation was completed, and then the roof needed to be repaired. This accident set us back a month, and it was going to be costly for the company. I decided it would be cheaper to work around the clock and bring in extra crews to complete the project on time. We ended up finishing two days early, but it was a very stressful month, indeed."