MockQuestions

Environmental Scientist Mock Interview

Question 22 of 25 for our Environmental Scientist Mock Interview

Get More Information About Our Environmental Scientist Interview Questions

Question 22 of 25

When have you had to change a major component of your project, due to new information being presented?

"I had a large project last month that was nearly complete when the client called to say that some of the needs provided were incorrect. Because of this, our team had to re-do the entire proposal. It took us an additional four days of work but, in the end, the client was delighted with our work, and it resulted in new opportunities for them."

Next Question

How to Answer: When have you had to change a major component of your project, due to new information being presented?

Advice and answer examples written specifically for an Environmental Scientist job interview.

  • 22. When have you had to change a major component of your project, due to new information being presented?

      How to Answer

      Being able to swivel the focus of your project is a necessary skill for your success as an environmental scientist. Talk to the interviewer about a time when a significant change occurred on a project. Consider how you handled the implementation of the new information.

      Written by Rachelle Enns on April 1st, 2021

      Entry Level

      "Last year we saw new federal regulations come through which affected 80% of our ongoing projects. We had to adjust our plans; however, we were able to deliver a timely product that met federal regulations."

      Written by Rachelle Enns on April 1st, 2021

      Answer Example

      "I had a large project last month that was nearly complete when the client called to say that some of the needs provided were incorrect. Because of this, our team had to re-do the entire proposal. It took us an additional four days of work but, in the end, the client was delighted with our work, and it resulted in new opportunities for them."

      Written by Rachelle Enns on April 1st, 2021

      Experienced

      "All of the time! As an experienced environmental scientist, I see many projects that need to be revisited and nearly scrapped in their entirety, at times. It can feel defeating; however, there is always something to learn through these events."

      Written by Rachelle Enns on April 1st, 2021

      Anonymous Interview Answers with Professional Feedback

      Anonymous Answer

      "The only experience I've had would be when I was in university. For example, when I would write a research article and new information came up I would essentially have to rewrite it so it was more dated. Although it can be disheartening; it shows there's always something to learn."

      Amanda's Feedback

      I can see where you're headed here. Consider strengthening your answer by sharing a specific example of a time when you had to revise your research. Or, choose another example of a time when you had to adapt based on new information. For example, if you volunteer for an environmental clean-up day, did new weather information ever cause you to adjust your plans? Has new information about environmental impacts ever caused you to redirect your efforts or conduct research in a new area?